Project Estimates
Posted on June 24th, 2010 by Mashooq Badar
This post was originally published here by Valtech UK consultant Mashooq Badar.
In my previous post on High Level Project Estimates, I talked about 3 points estimates to help provide an up-front estime of effort for a project. Aside from the effort estimate you also need to consider other aspects that the team will spend time on. The following are some aspects I consider with the kind of percentages (above the effort estimate) I have experienced. Note: these percentages are by no means standard or the norm they are essentially a rough guess based on the projects I have worked .
- Planning Meetings @ 10%
- Demos @ 2%
- Code Reviews @ 5%
- Retrospectives @ 5%
- Dark Mater @15%
- Bugs @15%
- New Technical Stories and Spikes @ 25%
- Change Requests (shouldn’t average more than 15%)
- Holidays and Sick Leave @ 5%
You will also need to consider Management Overheads as well as Business Analysts (if included in the team), QA/Functional Testing, Support and Maintenance (if required).